December 2012 – December 2013
Move IT were tasked to exit a client from two large serviced data centres over a 12 month period. Move IT were required to disconnect, de-rack and exit all equipment plus associated racks.
Both data centre site exits were scheduled to exit in a weekly parallel until complete. Total volume – approximately 1000x pallet spaces of equipment/racks. All access tickets and works tickets were all managed directly between Move IT and the data centre team.
Exit was achieved and our client successfully handed back the various data centre floors within the agreed timescale and budget.